Construction Closeout Checklist Builder
Standardized commercial project closeout register. Track O&M manuals, warranty binders, as-built redlines, commissioning reports, and lien waivers to verify administrative closeout readiness.
Zero cloud storage of project numbers, pricing, or documents. Data stays strictly inside your browser.
Project Specification & Header Data
Header metadata prints cleanly on exported reports and formal submittal covers.
bdp_tool_closeout_checklist). If using a public or shared computer, click “Clear Data” when finished. No data is ever transmitted to remote cloud servers.PROJECT CLOSEOUT & SUBSTANTIAL COMPLETION REGISTER
Valley Regional Ambulatory Center • Job #2026-VR-091
Contractor: BuildDesk General Contracting
Architect/Owner: Sloan & Heller Architects
Contract Value: $3,450,000 (Retainage: $345,000)
4 item(s) pending verification. Retainage release and final payment eligibility depend on contract requirements and required approvals.
Closeout Deliverable Register
7 Registered Items| Deliverable Title | Category | Spec Section | Responsible Party | Due Date | Status | Actions |
|---|---|---|---|---|---|---|
Certificate of Occupancy (Final CO / TCO) Final building, electrical, and plumbing inspections signed off by city. | Regulatory / Inspections | 01 77 00 | GC Project Manager | 2026-11-15 | ||
MEP Redline As-Built Record Drawings Under architect review; includes duct routing and circuit breaker updates. | As-Built Drawings | 01 78 39 | Precision Mechanical & Electrical | 2026-11-20 | ||
Rooftop Air Handling Units (RTU) O&M Manuals 3 bound hard copies + searchable PDF flash drive delivered to facility manager. | O&M Manuals | 23 00 00 | Apex Mechanical Services | 2026-11-15 | ||
20-Year TPO Membrane Manufacturer Roof Warranty Manufacturer field inspection completed 11/12; awaiting final signed certificate. | Warranties & Guarantees | 07 54 00 | Vanguard Roofing Systems | 2026-11-30 | ||
HVAC Testing, Adjusting & Balancing (TAB) Final Report Air balance certified within 10% design CFM tolerance across all diffusers. | Testing & Commissioning | 23 05 93 | Certified Air Balance Agency | 2026-11-15 | ||
Final Unconditional Lien Waivers (AIA G706 / G706A) 14 of 18 major subcontractor final lien releases in hand. | Financial & Lien Waivers | 01 77 00 | GC Controller & All 1st-Tier Subs | 2026-12-10 | ||
Spare Acoustical Tiles, Carpet Remnants & Touch-Up Paint Attic stock turnover receipt requires Owner facility manager signature. | Attic Stock Turnover | 01 78 46 | Drywall, Flooring & Paint Subs | 2026-11-25 |
Reconciling Final Scope Revisions & Drawing Changes?
BuildDesk Partners performs drawing revision quantity delta audits and scope proposal reviews to verify that all final change orders, deductive scope items, and as-built modifications are fully substantiated before contract closeout.